Installation
4-3
Distributed I/O Device ET 200M
EWA-4NEB780600602-06
4.1.2 Clearance Measurements
Rules
If you adhere to the minimum clearance measurements:
You will ensure that the S7-300 modules do not get too hot.
You will have adequate space for inserting and removing the S7-300 modules.
You will have sufficient space for running cables.
If you use a shield contact element, you can connect shielded cables directly
with the rail (see Section 5.2.4). This increases the height of the S7-300
mounting rack to 185 mm. You must, however, still maintain a clearance of
40 mm.
Clearance Measurements
Figure 4-2 shows you the clearance measurements to nearby cable ducts,
apparatus, cabinet walls etc. for an ET 200M installation.
If you use a shield contact element, the dimension specifications apply from the
lower edge of the shield contact element.
40 mm
40 mm
20
mm
20
mm
Figure 4-2 Clearance measurements for an ET 200M installation on a mounting rack
Installation Dimensions of the Modules
The dimensioned drawings of the S7-300 modules are contained in the Module
Specifications Reference Manual.
You can find the installation dimensions of the IM 153-x in Section 8.3.