Product Characteristics
4.2 Installation
SIMATIC NET PROFIBUS Optical Link Module OLM V4.0
22 Operating Instructions, 01/2013, C79000-G8976-C270-03
4.2.2 General information on commissioning
Unpack the OLM V4.0 and its accessories and check that the consignment is complete and
that there has been no damage during transportation. After unpacking, the device should be
acclimatized for some time to avoid condensation after to storage in cold surroundings.
First choose the network topology suitable for your requirements. Commissioning of the
modules then involves the following steps:
Checking and, if necessary, setting of the DIL switches.
Installation of the modules.
Connection of the power supply and, if required, connection of the signaling contacts.
Connection of the RS-485 bus line with installed bus connectors (if you use a bus
topology, remember that the terminating resistors in the connectors at both ends of the
line must be activated).
Connection of the optical bus lines.
Figure 4-1 View of the OLM from the top
Position of the DIL switches and of the terminal block for the power supply/signaling contacts/level
measurement. The figure shows the factory default setting of the DIL switches (switches S0, S1, S2, S3,
S4, S7 and S8 in position “0”, switches S5 and S6 in position “1”).