Commissioning and optimization (software)
7.1 Commissioning sequence
ET 200pro FC
84 Operating Instructions, 11/2007, A5E01100763B AA
Table 7-1 First commissioning and optimization
Steps Description Tool
1 Commissioning and optimizing the
frequency converter/motor
combination
Basic parameterization has already
been carried out when commissioning
the hardware (quick commissioning).
The motor type plate data and the
frequency converter factory settings
form the basis for this.
Motor data are entered;
Motor identification
Motor data measurement
Setting the V/f control (I-max
controller, slip compensation,
adaptation of the V/f characteristic)
Setting the frequency control (pre-
control, closed-loop PI controller)
Torque limits
STARTER at the RS232 interface
2 Commissioning and optimizing the
drive application
Frequency setpoint
Frequency limitation (skip frequency
bands, minimum and maximum
limitation)
Ramp function generator
Motor temperature monitoring
Brake control
Flying restart
Automatic restart
Load torque monitoring
STARTER at the RS232 interface
3 Commissioning the communication
between the S7 CPU and frequency
converter:
PROFIdrive
Fieldbus parameters
Telegram failure time
Integrating the S7 program for the
cyclic parameters into the S7 CPU
STEP 7 via fieldbus on the PLC
STARTER at the RS232 interface
4 Commissioning fail-safe functions Parameters
Password protection
STARTER at the RS232 interface
Table 7-2 Standard commissioning
Steps Description Tool
With STARTER STARTER at the RS232 interface Transferring the parameters and
settings to other frequency converters
With MMC MMC