3 Installation and Commissioning
B−15
CP 343-1 Advancedfor Industrial Ethernet / Manual Part B
Release 06/2008
C79000-G8976-C202-04
3 Installation and Commissioning
3.1 Procedure / steps
Step Explanation / meaning
1. Install the CP on the S7 standard rail.
2. Establish the connection via the enclosed bus
connector to the backplane bus.
Slots 4 to 11 are permitted for the CP in racks 0 to 3
(connected by IM 360/361).
Proceed as in the sections dealing with setup and
wiring, described in detail in /1/.
Note
The CP cannot be used in an extension rack that is connected via the IM 365! Reason: The required
communication bus is not connected to the extension rack via the IM 365.
3. Connect the CP to the power supply. Follow the steps as described in detail in /1/ when
wiring between the power supply and the CPU.
Notes
S The CPU, CP and IM (if one exists) must be connected to the same power supply.
S Only wire up the S7-300 / C7-300 with the power switched off!
4. Connect the CP to Industrial Ethernet.
5. The remaining steps in commissioning involve
downloading the configuration data.
To download the configuration, you can connect
the PG as follows:
S via MPI
S via Industrial Ethernet
For further details, refer to the general Part A of
this manual:
− Addressing the first time (IP address
assignment / node initialization)
Note: Addressing for the first time is
possible only over the PROFINET interface.
− Downloading the defined configuration
The PG/PC requires a LAN attachment, for
example via a CP 1613 or CP 1411 and must have
the necessary software (for example the S7-1613
package or SOFTNET IE). The TCP/IP protocol or
ISO protocol must be installed. The protocol used
must then be applied to the S7ONLINE access
point.